| Client: Cloverland Electric Cooperative Location: Dafter, Michigan
Project consisted of the reconstruction of 20 miles of three-phase overhead distribution line. A total of five RUS distribution work plan rebuilds were included in this project. Circuits from 12.5kV & 24.9kV substations were included in the reconductoring projects. Conductor size was increased to #336.4 ACSR to provide circuit capacity for backing up nearby substation circuits and to minimize voltage drop.
Engineering services included:
- Distribution line design
- Staking sheet preparation
- Construction assembly drawings
- RUS 790 Contract documents
- Material procurement
- Construction staking
- Construction observation
- Inspection for RUS219 approval
- RUS Closeout documentation
|