| Client: Holland
Board of Public Works
Location: Holland, Michigan
Project consisted of the reconstruction of
one-half mile of single circuit 138kV transmission line for road
widening and bridge reconstruction. Various route and construction
options were analyzed to maintain the existing 138kV river crossing,
including ACCC composite conductors and underground 138kV cables. The
138kV transmission line was constructed overhead with traditional round
wood and self-supporting tubular steel structures. Three steel
transmission structures were attached to a new pedestrian bridge to
allow for existing vehicle bridge reconstruction.
Engineering services included:
- Project planning & cost estimating
- Route selection & coordination of
topographic survey
- ACCC Conductor analysis
- Transmission line design
- Material procurement
- Bidding & contract documents
- Bridge Construction & MDOT
Coordination
- Construction observation

|