| Client: Wolverine
Power Cooperative, Inc.
Location: Portland, Michigan
Project consisted of the relocation of 3/8
mile of single-circuit 69kV transmission line for the expansion of a
poultry farm. Design constraints included easement limitations,
building proximity, and stock material. Project was fast-tracked due to
construction schedules at the poultry farm. The transmission line was
designed around in-stock material to maintain the required construction
schedule.
Engineering services included:
- Topographic & boundary surveying
- Transmission line design
- Plan & Profile drawings
- Assembly drawings
- Material procurement
- Bidding & contract documents
- Construction observation
- Record drawings
- Closeout documentation
|